IN6.2.1 - Loganholme Wastewater Treatment Plant (WWTP) Stage 8. Beenleigh WWTP Close |
June 2024 |
Completed |
At the end of the 2023/2024 financial year, scheduled works for the project have been delivered to complete critical Stage 8 upgrades to the Loganholme Waste Water Treatment Plant.
The Stage 8 upgrade will be operational with the diversion of flows from the number 3 oxidation ditch.
Highlights of the year's achievements include completion of the following:
- fine screens and associated infrastructure
- bioreactor (two trains) and associated structure, including a flow selector, bioselector, anaerobic, anoxic and aeration zones
- membranes (four trains of nine installed membrane modules with provision for one additional membrane per train) and associated infrastructure
- blower room housing blowers for the bioreactor and membrane tanks and air compressors
- switchroom housing switchboards, control panels and a SCADA workstation
- chemical storage and dosing systems including sodium hypochlorite and citric acid
- new outfall pipeline and headwall structure
- general purpose pump station for plant drainage and wastewater flows
- two standby emergency generators
- new power supply connection from Energex including construction of remote monitoring unit, installation of high voltage power supply cables and two power distribution transformers.
The project has now reached a stage of practical completion. |
IN6.2.2 - Water and Wastewater Capital Works Program |
June 2024 |
Completed |
At the end of the 2023/2024 financial year, all projects and renewal programs on the Water and Wastewater Capital Works Program scheduled for construction completion have been delivered.
A total value of $130.2 million was delivered over the financial year against an approved budget of $182.0 million.
The variance is due to delayed construction commencement on a number of identified wastewater projects in Logan South due to extended time frames for environmental approvals (Environmental Protection and Biodiversity Conservation Act) and easement acquisitions. These projects were subsequently commenced after approvals were obtained, with progression to completion in 2024/2025 as scheduled.
Commencement of sustanability projects which involved solar were also put on hold pending Council's Energy Request for Proposal process (RFP). Construction commencement of the new Logan Water Depot at Loganholme was held off to allow for increased climate resiliency in the design, and construction has now commenced.
Some highlights of the year's achievements include completion of the following projects and renewals programs:
- Rai Drive (Crestmead) Wastewater Pump Station and Conveyance
- Loganholme Wastewater Treatment Plant Stage 8 Upgrade
- Alfred Street Wastewater Pump Station Emergency Equipment
- PH Monitoring and Control (Woodhill) Project
- Nestor Drive (Loganlea) DN375 Pipeline Renewal
- Seqwater Booster Water Pump Station and Pressure Reducing Valves Installation
- Logan Reserve Water Pump Station and Pub Lane Network Improvements
- Annual Water Network Improvements and Extension Program
- Annual Supervisory Control and Data Acquisition (SCADA) Upgrade Program
- Annual Water Facility Renewal Program
- Annual Water Pressure and Leakage Management Program
- Annual Water Network Improvements and Renewal Program
- Annual Wastewater Overflow Management Program
- Annual Wastewater Treatment Renewal and Upgrade Program
- Annual Wastewater Network Renewal and Improvements Program.
The programme of works for the financial year 2023/2024 is complete. |
IN6.3.1 - 2023/2024 Parks Capital Works Program delivery |
June 2024 |
Completed |
The Parks Capital Works Program Delivery achieved delivery of $27.9 million against an approved budget of $24.9 million (excluding donated assets) for the 2023/2024 financial year. This represents an investment of 112% and is the largest capital works program delivered by the Parks Branch to date. A key contributor to the overspend was the early acquisition of land for the future Logan Metro Sport Complex of $4.0 million.
Key projects completed for the year in this program of works include:
- Alexander Clarke Playground
- Mabel Park
- Riverdale Park
- Eagleby Wetlands
- Ison Park Pump Track
- Streetscaping on Beenleigh Redland Bay Road
- Lincoln Green Upgrade
- Elm Park Upgrade.
The programme of works for the financial year 2023/2024 is complete. |
IN6.6.1 - Road and Drainage Capital Works Program |
June 2024 |
Completed |
At the end of the 2023/2024 financial year, delivery of the Capital Roadworks and Drainage Program achieved $148.2 million in overall expenditure. This was in line with forecasts at 106% of the overall expenditure target.
Notable projects under construction or delivered throughout the year include:
- Loganlea Road Upgrade, Loganlea
- Chambers Flat Road Upgrade, Chambers Flat
- Jimboomba Stage 2 Local Road Kerb and Stormwater Upgrades
- Gunungai Drive Cycleway, Slacks Creek
- Stage 1 and 2 of the Cowper Avenue Catchment Master Drainage Project, Eagleby
- Stages 1 to 5 of the Kelly Street Catchment Master Drainage Project, Eagleby
- Bobermien Road Local Road Upgrade, Logan Village
- Leopardwood Road Local Road Upgrade, Cedar Grove
- Station Road Cycleway, Loganlea
- Storey Road and Manuka Road Local Road Kerb and Stormwater Upgrades, Logan Village
- Chambers Flat Road and Muchow Road Intersection Upgrade, Marsden
- Grand Plaza Drive & Eastern Drive Cycleway, Browns Plains
- Cinderella Drive Cycleway, Springwood
- Cinderella Drive and Dennis Road Intersection, Springwood
- Tully Timber Bridge Replacement, Lyons
- $30.7 million in asphalt resurfacing, spray sealing works and pavement rehabilitation at numerous locations across the city.
The Capital Roadworks and Drainage Program delivers enhanced transport and drainage infrastructure across the City of Logan. The Program delivers infrastructure upgrades to cater for improvements and growth across the city as well as renewal of the existing infrastructure network.
The programme of works for the financial year 2023/2024 is complete. |
IN6.7.1 - Monitoring room expansion investigation |
June 2024 |
Completed |
At the end of the 2023/2024 financial year, the investigation into the expansion of the Logan Safety Camera Program Monitoring Room was completed.
As part of the investigations during this period, engagement occured with the Corporate Property and Information Technology Services branches regarding the minor redesign of the original Monitoring Room space to allow for future growth and expansion. The expansion includes:
- new desk spaces
- new desk monitoring screens
- replacement of the video wall
- realignment of the Monitoring Room to better utilise space.
The outcome of the investigation highlighted a requirement for consideration of, and alignment with, the Council Administration Centre (CAC) accommodation review. This will include consideration of the potential relocation of the Safety Camera Monitoring Room.
This project is now complete. |