Infrastructure - Quarter 3, 2023 / 2024

Project Target Status Commentary
IN6.2.1 - Loganholme Wastewater Treatment Plant (WWTP) Stage 8. Beenleigh WWTP Close June 2024 On Track
The following activities commenced in March 2024, and are continuing into April 2024:
  • Bioreactor/ Membrane tank/ permeate tank commissioning
  • Finescreens odour covers installation
  • Grouting around site ongoing
  • Miscellanous slabs installation around the site.

The following new activies will commence in April 2024:
  • Roadworks
  • Bypass manhole construction.

Overall, the project is on track for construction completion and comissioning as scheduled.
IN6.2.2 - Water and Wastewater Capital Works Program June 2024 Monitor
As at the end of March 2024, the expenditure on the Water and Wastewater Capitals Works Program was $94.01 million against a phased budget of $110.79 million. 

The construction commencement of a number of wastewater projects in Logan South was delayed due to extended time frames for environmental approvals and easement acquisitions. 

The program will still be delivered, however there will be budget carry-overs into the next financial year.
IN6.3.1 - 2023/2024 Parks Capital Works Program delivery June 2024 On Track
At the end of the third quarter of 2023/2024, delivery of the Parks Capital Works Program has achieved a year to date spend of $17.6 million against a forecast in the adopted budget of $23.2 million, representing 75 perfent completion of the annual program.

Key projects in construction include Fitzgerald Avenue Streetscape Upgrade, Acacia Park and Alexander Clarke Park Stage 3.

Current risks to the program are resourcing (both internal labour and contractors). These risks are being proactively managed through Parks Pre Qualified Supplier Panel and value/scope management. Construction cost inflation has reduced and is no longer considered a key risk for the program.
IN6.6.1 - Road and Drainage Capital Works Program June 2024 On Track
At the end of the third quarter of 2023/2024, delivery of the Capital Roadworks and Drainage Program achieved $98.9 million in overall expenditure. This was ahead of anticipated expenditure targets by 3 percent.

Notable projects under construction throughout March include:
  • Loganlea Road Upgrade, Loganlea
  • Chambers Flat Road Upgrade, Chambers Flat
  • Jimboomba Stage 2 Local Road Kerb and Stormwater Upgrades
  • Bobermien Road Local Road Upgrade, Logan Village
  • Leopardwood Road Local Road Upgrade, Cedar Grove
  • Station Road Cycleway, Loganlea
  • Storey Road and Manuka Road Local Road Kerb and Stormwater Upgrades, Logan Village
  • Chambers Flat Road and Muchow Road Intersection Upgrade, Marsden
  • $3.3 million in asphalt resurfacing, spray sealing works and pavement rehabilitation at numerous locations across the city.

The Capital Roadworks and Drainage Program delivers enhanced transport and drainage infrastructure across the City of Logan. The Program delivers infrastructure upgrades to cater for improvements and growth across the city as well as renewal of the existing infrastructure network.
IN6.7.1 - Monitoring room expansion investigation June 2024 On Track
During the third quarter of 2023/2024, realignment of the monitoring room has progressed and underfloor investigations are underway.