IN6.1.1 - Captial Works Design Program |
IN6.1 |
June 2025 |
On Track |
There were 37 detailed engineering designs scheduled for completion in the 2024/25 program.
By the end of the second quarter of 2024/25, a total of 16 design projects were completed and issued for construction. |
IN6.1.2 - Design of Bethania to Logan Village rail trail |
IN6.1 |
June 2025 |
On Track |
Detailed design for the Bethania to Logan Village Rail Trail is on track to completed by June 2025.
During the detailed design, it was determined that the funding allocation to deliver the Bethania to Logan Village Rail Trail was insufficient. Council endorsed to write to the state government (TMR) seeking additional funding for the Rail Trail in full.
Council has submitted a request to TMR seeking a variation and awaiting their response.
Negotiations are on-going with Palm Lakes Resort regarding security / safety measures for Palm Lakes. |
IN6.1.3 - Road and Drainage Capital Works Program |
IN6.1 |
June 2025 |
On Track |
At the end of the second quarter 2024/25, delivery of the Capital Roadworks and Drainage Program achieved $70.2 million in overall expenditure. This is ahead of planned budget expenditure, at 104% of adopted budget milestone targets.
Notable projects under construction throughout the quarter include:
- Loganlea Road Upgrade from University Drive to Pacific Motorway (6 lanes)
- Chambers Flat Road Upgrade, Chambers Flat from Mount Lindesay Highway to Kings Way
- Stormwater drainage upgrades to Stage 1 and 2 of the Cowper Avenue Catchment Master Drainage Project, Eagleby
- Stormwater drainage upgrades to Stage 1 to 5 of the Kelly Street Catchment Master Drainage Project, Eagleby
- Park Ridge Road, Clarke Road and Lindenthal Road, Park Ridge Intersection Signalisation
- Teviot Road and Cusack Lane, Riverbend and South Maclean Intersection Signalisation
- Teviot Road, Middle Road to Greenbank Road – Stage 1A
- Chambers Flat Road (Holloway to Kenny Road) Safety Improvements, Chambers Flat
- Alamein Street, Main Street and George Street Intersections Upgrade.
- Woodlands Drive - Stormwater Drainage Upgrade Stages 10, 11 & 12.
- Underwood Road Bus Turnaround, Priestdale
- Goodna Road Carpark Upgrade, Greenbank
- Beenleigh Road Widening, Underwood
- Pavement Rehabilitation works to the value of $4.7m at numerous locations across the city.
The Capital Roadworks and Drainage Program delivers enhanced transport and drainage infrastructure across the City of Logan. The Program delivers infrastructure upgrades to cater for improvements and growth across the city as well as renewal of the existing infrastructure network. |
IN6.1.4 - Way2Go Refresh |
IN6.1 |
June 2025 |
On Track |
During the second quarter of 2024/25, progress on the Way2Go Refresh included the following activities:
- drafting of consultancy scope and Request for Quote (RFQ) document commenced
- project governance framework developed and discussed with Project Sponsor
- benchmarking with Local Government Authorities (LGAs) on contemporary approaches to Integrated Transport Strategies (ITS) commenced.
In early 2025, we aim to present an audit report and ITS update scope to the Executive Leadership Team (ELT). |
IN6.2 - Review and update Council’s Water Netserv Plan |
IN6.2 |
June 2025 |
Completed |
During the second quarter of 2024/25, Logan Water provided notice to the Planning Minister (in accordance with section 99BRAB (5) of the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009 (SEQ Water Act), that Council adopted the Water Netserv Plan Part A and its Connections Policy in December 2024.
The project to undertake a formal review of the Water Netserv Plan Part A and its Connections Policy is now completed and the Water Netserv Plan (Part A): 2022–2026 and Connections Policy are now published on Logan City Council's website.
This project is now complete. |
IN6.2.1 - Water and Wastewater Capital Works Program |
IN6.2 |
June 2025 |
Monitor |
At the end of the second quarter of 2024/25, the Water and Wastewater Capital Works Program expenditure was $64.70 million against a phased budget of $81.28 million. Expenditure will continue to ramp up as more projects enter the construction phase.
The commencement of the various green energy projects was delayed pending the signing of the agreement with Council's preferred energy partner. With the signing of the agreement, the green energy projects have commenced and are in various stages of development.
In addition to various water and wastewater asset renewal projects, good progress has also been made on a number of other significant wastewater projects. This includes the commissioning of the Loganholme Wastewater Treatment Plant Stage 8 Upgrade and pump station upgrades to enable diversion of flows from the Beenleigh Wastewater Treatment Plant to the Loganholme Wastewater Treatment Plant. |
IN6.3.1 - 2024/2025 Parks Capital Works Program delivery |
IN6.3 |
June 2025 |
On Track |
Parks have achieved a capital spend of $6.7 million against a year to date budget of $12.4 million.
Key variances to the spend are projects completed ahead of schedule and projects delayed which will now be delivered in the second half of the financial year.
The variations between expenditure and spend will be corrected through the budget amendment process. |