High performing organisation - Quarter 4, 2021 / 2022
Project | Target | Status | Commentary |
---|---|---|---|
HP7.1.1 - Property rating strategies and framework
|
March 2022 | Not Proceeding |
A decision was made by Council in the second quarter to remove this project from the Operational Plan (minute# 16/2022).
|
HP7.2.1 - 213 Queens Road redevelopment
|
June 2022 | Completed | During the fourth quarter Stage 1 of the Queens Road Redevelopment project was completed and comprises a new staff entry and crossover, car impound yard, staff car park, road and underground infrastructure (fire, water and power), and long-term stay impound kennels. Commencement of Stage 2 was delayed due to extensive heavy rain and weather events impacting construction. These delays are within the scope of the contract. A revised construction program will see elements of Stage 3 incorporated into Stage 2. Stage 2 is scheduled to commence 21 July 2022. No risks or issues specific to the project or development site were identified during quarter four. There has been negligible impact to depot operations during quarter four. |
HP7.2.2 - Community Engagement Strategy Action Plan
|
December 2021 | Completed | The Community Engagement Strategy Implementation and Action Plan (document) is complete. (DM# 15250475) The Plan will assist the Community Engagement Program to prioritise, monitor and adapt initiatives under the three priority areas of the Strategy. The Community Engagement Strategy for the City of Logan must be implemented by the end of 2024. Timeframes for all initiatives included in the Community Engagement Strategy will be detailed in the Plan in order of priority. This will be done in collaboration with the Community Engagement Program. The final Plan will be version controlled and adapted where necessary to meet changing community needs. The Community Engagement Strategy Implementation and Action Plan includes initiatives, priorities, timelines and responsibilities. The monitoring, reporting and evaluation processes will be determined on a project-by-project basis and approved by the Customer Experience and Community Engagement Manager. Delivery of the Plan's actions will be ongoing until 2024. |
HP7.2.3 - Community Engagement Framework
|
June 2022 | Completed | As at the end of the fourth quarter, the following was achieved:
Under the Get Ready Funding:
|
HP7.2.4 - Disaster Management Capability and Capacity Framework
|
June 2022 | Completed | As at the end of the fourth quarter, the following was achieved:
|
HP7.2.5 - Recruitment
|
June 2022 | Completed | The Talent Acquisition Partner team is now funded appropriately and the team structure and role requirements have been confirmed. There has been some turnover in the team with replacements currently being sought, however this is indicative of current turnover trends across Council and other external organisations. Further workflow and process improvements, including benefit realisation will continue as business as usual with portfolio management tracking and inserted into ongoing Branch Business plans |
HP7.2.6 - Procurement Model Review Stage 3
|
June 2022 | Completed | This project was completed in the third quarter. As at the end of the third quarter:
What was achieved?
Challenges
|
HP7.3.1 - Corporate Innovation Strategy
|
June 2022 | Completed | 2022 marked the third year of the implementation roadmap for Council's endorsed Corporate Innovation Strategy (Minute No: 157/2019). The following summary highlights the performance of the Corporate Innovation Program's 3 core functional areas at financial year end: Corporate Innovation Service: The Corporate Innovation Team designed and facilitated problem solving services to support 35 project teams and engaged 475 staff across every directorate in Council. Project teams were supported to better frame problems, understand the lived experience and impact of problems for customers/users and ideate and prototype potential solutions. Project teams were coached in the application of tools and techniques across problem framing, problem discovery, ideation and prototyping. At the end of 21/22, customer value survey results for this service is tracking at 90% favourability, resulting in improved performance of 2% compared with the previous financial year (88%). Innovation Culture and Capability. Some of the key highlights for this service include the monthly (excluding Dec/Jan) Lunch and Learns. Attended by 325 staff (averaging 32 staff per month), 26 Lunch and Learn sessions, covering 10 topics were delivered., Lunch and Learn customer value is tracking at 90% favourability rating, an improved performance of 6% compared with 20/21 (84%). 94% of staff surveyed also agreed they are likely to attend future Lunch and Learns. The online Introduction to Problem Solving training program was also delivered this year. Launched in November 2021 and built in Council's Logan Learning Hub, there are currently 78 staff enrolments. The LDP Hackathon was another initiative delivered in partnership with the People and Culture Branch this year. Involving 22 staff from the 2022 Leadership Development Program, the hackathon provided capability development across innovation tools and methodologies underpinned by Lean, Agile and Human Centred Design. The Hackathon uses an experiential learning model, exposing emerging leaders in the application of leadership skills of the future including critical analysis, systems thinking, agility and adaptive thinking, collaboration, storytelling and human centred design thinking. Participant survey results were 95% favourability rating (an improved performance of 1% from 2021 and 9% from 2020). 100% of those surveyed also agreed they would apply the tools and techniques learnt back in the workplace (up 5% from 2021). The 2021 Hackathon initiative was recognised with a 2021 Employee Excellence Award (runner up). A facilitator resource kit (Energiser/icebreaker manual and session plan run sheets) and a Do-It-Yourself suite of problem-solving tools (templates and 'How to' videos) was launched in this financial year as additional products for the organisation. Innovation Communication and Engagement: This service continued to drive a culture of innovation across the organisation in the 21/22 financial year. Some of the key highlights include the launch of the bi-monthly Innovation Unearthed (IU) e-magazine in July 2021. In 20/21, 6 editions were published and distributed and has amassed 368 staff subscribers. The IU e-magazine consistently outperformed industry benchmarks across open rates and click through rates, representing high staff engagement. At the end of 20/21, IU open rates were 34.76% (industry benchmark 20.5%) and click through rates were 14.61% (industry benchmark 1.8%), which demonstrates that the IU content resonates well with our staff. IU published more than 80 stories and further promotion occurred through the Daily Buzz and were viewed 2,597 times by staff. More than 200 artefacts were created over the financial year to promote and drive innovation across the organisation. |
HP7.3.2 - TechOne to the Cloud
|
June 2022 | Completed | As at the end of the fourth quarter the TechOne to the Cloud project has successfully delivered the key goals of the project set out for this financial year. This includes:
Phase 2 of the Project will begin 01 July 2022 with a target for completion by the end of December 2022. |
HP7.3.3 - Enterprise Asset Management System
|
June 2022 | Completed | As at the end of the fourth quarter, planned activities for the initial stages of this project were completed per the project schedule. The EAMS Detailed Business Case has been finalised and endorsed by ELT to progress to Governance Committee on 20 July. This ultimately completes the scope of work for the 2021/22 financial year. The EAMS Program will proceed into the implementation of the solution as per the business case. The implementation will focus on the foundational components needed for a successful EAMS delivery and will be tracked under HP7.4.3 for the 2022/23 financial year. |
HP7.3.4 - Corporate project management practices
|
June 2022 | Completed | As at the end of the fourth quarter:
|
HP7.4.1 - Change Framework
|
June 2022 | Completed | As at the end of the fourth quarter, the last year has seen considerable progress in Council's commitment to strengthen change capability across the organisation, designed to enhance project outcomes for our community. Our change capable internal resource pool is both deeper and wider across leaders and staff. In addition, our change methodology has been further embedded, supported by effective tools, resources and sustainable ways of working. The current tranche of change capability uplift has therefore been successfully completed. |
HP7.5.1 - Corporate performance reporting
|
June 2022 | Completed | As at the end of the fourth quarter a Corporate Plan performance dashboard has successfully been delivered. This allows Council to track the delivery of the Corporate Plan in terms of delivering projects against its:
A first for Council, the dashboard provides a centralised location for project performance information that automatically aggregates with each new financial year. When the Corporate Plan reaches its end-of-life (2026), we will be able to see what has been delivered over its 5-year lifespan. The project has also delivered a Performance Management dashboard prototype. Building off the work presented to Council and ELT in November 2021, and their feedback, the prototype takes a balanced view of performance across the organisation across key areas including:
The intention of the prototype is to demonstrate the capabilities and possibilities of consolidating organisational-level KPIs into one place.
|
HP7.5.2 - Certified Agreement negotiations
|
June 2022 | Completed | As at the end of the fourth quarter the Logan City Council Certified Agreement 2022 has now been certified by the Queensland Industrial Relations Commission. This agreement will remain in operation to 22 April 2025. The parties (Unions and Council) to the agreement will seek to open negotiations for a replacement agreement no more than 6 months prior to the expiry date. |
HP7.5.3 - Delegations review
|
April 2022 | Completed | On 22 June 2022 the new framework for Council to CEO delegations was adopted by Council. This has been completed in advance for the deadline for annual review. The framework is therefore complete, with more work now to be done to implement the supporting technology solution and the CEO to officer delegations. |
HP7.6.1 - Strategic Accommodation Plan
|
June 2022 | Completed | The project status is completed in line with deliverables. The Stage 1 draft report was presented to Council officers for feedback. Council officers provided feedback and a completed report has been presented to Council officers. The report details a proposed strategic accommodation model for Council consideration. Next steps - the report will be presented to Council's Executive Leadership Team for their support and Stage 2 (detailed implementation) will be commenced in the new financial year. |
HP7.6.2 - Strategy addressing greywater services causing amenity issues
|
June 2022 | Completed | As at the end of the fourth quarter:
|
HP7.7.1 - Advocacy Action Plan
|
June 2022 | Completed | At the end of the fourth quarter the Advocacy Program had completed implementation of its 2022 Federal Election Advocacy Action Plan. The Advocacy Program is compilng an evaluation report and will report to Committee/Council on the outcomes of this campaign in July 2022. |