Environment - Quarter 4, 2023 / 2024

Project name Target Status Commentary
EN3.1.1 - Logan and Albert River Litter Clean Ups June 2024 Completed

During the 2023/2024 financial year, the Logan and Albert Litter Clean ups achieved the following:

  • The Logan River Clean Up program delivered the monthly clean-up of floating and bank bound litter along the Logan River, from Riedel Park (Carbrook), upstream to Anzac Avenue Bridge (Logan Village).
  • The clean-up of large debris from the Logan and Albert Rivers was undertaken from late January through to mid-February, and the associated reports were provided.
    • Approximately 21 tonnes or 57.8 cubic metres of waste was collected and disposed of, as part of this project.
    • The collected waste comprised a variety of large items including foam wrapped in concrete, intermediate bulk containers, partially sunken boat, concrete drain, tyres, pool, shed and timber.
All 2023/2024 Logan and Albert Litter Clean up projects have been delivered.

This project is now complete.
EN3.2.1 - Riverbank Restoration Projects June 2024 Completed During the 2023/2024 financial year, the following Riverbank Restoration dedicated projects were delivered:
  • planting works continued and were completed at Area 3A, Alexander Watt Park (5,408 plants)
  • planting works were undertaken at Logan River Parklands Stage 4 Riparian Rehabilitation project (2,508 plants)
  • planting works were undertaken at Riverdale Park Stage 4 Riparian Rehabilitation project (800 plants)
  • planting works were undertaken at Albert River Park Stage 2 Riparian Rehabilitation project (970 plants)
  • infill planting works were undertaken at Albert River Park Stage 1 Riparian Rehabilitation (200 plants)
  • Conservation and Ecosystem Management Trainee group, Reclink, assisted with on-site weed and rubbish removal works at Belivah Creek and Albert River Park and assisted in planting Area 3A Belivah
  • maintenance works were undertaken at previously planted Logan and Albert River restoration sites                                
  • Sebring Park Riverbank planting completed (5,000) on the Logan River and is now on maintenance.

All 2023/2024 riverbank restoration projects have been delivered.

This project is now complete.
EN3.3.1 - Tree Planting Offset Projects June 2024 Completed During the 2023/2024 financial year, 26,700 trees were planted through the environmental offset program. 

Throughout the year, the following tree planting offset projects were delivered:
  • ongoing maintenance works on 100 hectares of offset planted land continued
  • Ooah Park Stage 1 tree planting project was completed and the stage 2 contract was awarded ensuring best value for money to Council
  • Sebring Park offset planting project completed
  • Denman Court Park Environmental Offset tree planting project was  awarded to a supplier through evaluation process that determined best value for money to Council.
All 2023/2024 tree planting offset projects have been delivered. 

This project is now complete.
EN3.4.1 - Environmental conservation partnerships June 2024 Completed During the 2023/24 financial year, the Environmental Conservation Partnerships (ECP) achieved the following:
  • 1,082 members in total, participating in the program
  • 132 new Habitat Connections members joined the program - 593 properties in total (26 properties deregistered from the program)
  • 29 new Land for Wildlife members joined the program - 489 registered Land for Wildlife properties in total (12 properties deregistered from the program)
  • 2 new Formal Agreements - 31 properties in total (Voluntary Restoration Agreement, Voluntary Conservation Agreement and Voluntary Conservation Covenant)
  • 77 Land for Wildlife property revisits were conducted
  • 1,414 individual community engagement interactions were provided to ECP members
  • 30.55 hectares have been added to the Land for Wildlife Habitat network (total is 6,363 hectares)
  • 400 ECP members submitted orders for annual conservation incentives comprising:
    • 11,321 native plants
    • 41 nest boxes
    • 64 resource books
    • 91 herbicide packs
  • 8 threatened species were recorded on Land for Wildlife properties (19 threatened species have been recorded in total)
  • Queensland Feral Pest Initiative Grant funding was awarded to Logan City Council to the value of $34,000. Instalments 1 to 3 of 4 have been paid to Council. Videos have been completed
  • OXCLEP phase 3 properties were visited and final on-ground works completed. Phase 4 landholders have been engaged and landholder field day delivered.
All 2023/24 Environmental Conservation Partnerships projects have been delivered.

This project is now complete.
EN3.6.1 - Energy efficient lighting upgrades June 2024 Completed The Energy Efficient Lighting project was completed by May 2024, with 100% of initiatives completed at all sites identified within the project scope.

Highlights for the year include:
  • Libraries (Marsden, Hyperdome, Logan North) and Logan North Aquatic Centre were upgraded.
  • The Health Climate and Conservation branch undertook this project in collaboration with Sports and Community Infrastructure and Libraries and Creative Industries.
  • Benefits of this project include energy savings, reduced carbon emission, electricity cost savings, maintenance cost savings, improved staff and user experience.
  • 576 lights were replaced which is estimated to decrease electricity charges by over $6,500 per annum and reduce carbon emissions by approximately 40 tonnes.
  • Cost savings from the replacement are directly returned to the relevant Branches.
This project is now complete.
EN3.6.2 - Sustainable Solutions June 2024 Completed The investigation to identify options for delivering sustainable outcomes in the way Logan Water delivers its services was completed in June 2024.

Outcomes from the investigation informed initiatives for delivery, including:
  • A number of sustainability focussed initiatives have been identified and will be progressed with the support of our preferred Energy Partner following negotiation and award of Council's Energy Request for Proposal (RFP) process.
  • Most notable among the initiatives is the upgrade of High Voltage (HV) assets at the site to meet the needs of this critical infrastructure and future proof the facility. This upgrade will also include the integration of Solar and Battery Energy Storage System (BESS) to improve sustainability outcomes from Council's treatment operations.
  • A preferred Energy Partner has been selected and Logan Water is working closely with them to finalise associated agreements.
  • Loganholme wastewater treatment plant solar has progressed the design for solar and battery co-location.
  • The interfaces with Energex and the planned HV upgrade of Loganholme Waste Water Treatment Plant have been considered in the solar and battery design.
This project is now complete.
EN3.7.1 - Solar Panel Recycling Service June 2024 Completed At the end of the 2023/2024 financial year, the provision of an end-of-life solar panel recycling service for the community has been established.

Following a robust procurement process, a contractor has been appointed to provide a solar panel recycling service, which will commence 1 July 2024.

Highlights from the project include:
  • review of potential local solar panel recyclers and other options
  • evaluation of feasibility of amalgamation of solar panel recycling with other related contracts such as e-waste and batteries
  • Request for Quote issued March 2024, which included recycling provision for general e-waste, medium-large lithium batteries and solar panels
  • selection of preferred contractor to deliver the recycling service.
This project is now complete.