Economy and growth - Quarter 3, 2023 / 2024

Project Target Status Commentary
EG5.4.1 - Olympics Legacy Venue Business Case June 2024 Completed
Responsibility for the delivery of the business case for the Olympics Legacy Venue has transitioned to the Queensland Government.

This project is now complete.
EG5.5.1 - Logan Plan 2025 State Interest Review June 2024 Monitor
The draft new planning scheme was delivered to the Queensland Government (State) in September 2023 for the first State Interest Review, in accordance with planned delivery for the 2023/2024 financial year.

Responses have been provided to the State's requests for information as part of first State Interest Review. These totalled 134 items, including some which were received on 2 February 2024 relating to the updated South East Queensland (SEQ) Regional Plan.

Advice is awaited from State regarding the responses provided to their information requests. Further advice from State is also pending regarding their direction provided late January 2024, requiring an alignment amendment to our current planning scheme (Logan Planning Scheme 2015) associated with the updated SEQ Regional Plan.  

Work continues towards preparing for public consultation for the new planning scheme, anticipated to occur in the 2024/2025 financial year.
EG5.8.1 - Digital Infrastructure and Connectivity Program June 2024 Completed
At the end of quarter 2, the identified program of works for the Digital Infrastructure and Connectivity Program is complete from both a Logan City Council and State Government perspective.

Highlights of the program included:
  • engagement with potential participants completed
  • network detailed design completed
  • fibre cable construction laid and installed
  • internet service to participating properties turned on.

The final report for the State Government, providing a comprehensive summary of the project, is due to be lodged by mid-March 2024. This is the final step in the project.

This project is now complete.