Economy and growth - Quarter 2, 2023 / 2024

Project name Target Status Commentary

EG5.4.1

Olympics Legacy Venue Business Case

June 2024 Completed Responsibility for the delivery of the business case for the Olympics Legacy Venue has transitioned to the Queensland Government.

This project is now complete.

EG5.5.1

Logan Plan 2025 State Interest Review

June 2024 On Track During the second quarter of 2023/2024, the project team worked through the 131 items raised by the State Government in their information request. State Government also flagged that a supplementary information request will be made once the Regional Plan is updated.

Towards the end of the quarter, the State Government issued a pause notice requesting more information on the policies within the Logan Plan.

The Branch is working on providing the required information in acccordance with the State Government request.

EG5.8.1

Digital Infrastructure and Connectivity Program

June 2024 Completed Interpretation and Response:
At the end of quarter 2, the identified program of works for the Digital Infrastructure and Connectivity Program is complete from both a Logan City Council and State Government perspective.

Highlights of the program included:
  • engagement with potential participants completed
  • network detailed design completed
  • fibre cable construction laid and installed
  • internet service to participating properties turned on.

The final report for the State Government, providing a comprehensive summary of the project, is due to be lodged by mid-March 2024. This is the final step in the project.

This project is now complete.