EG5.5.1 - Logan Plan 2025 State Interest Review |
June 2024 |
On Track |
This project contributes to the progression of Logan Plan 2025.
The draft scheme was delivered to the Queensland Government for State Interest Review in September 2023.
Council will work with the State to achieve endorsement for public consultation in 2024/2025.
|
EG5.8.1 - Digital Infrastructure and Connectivity Program |
June 2024 |
On Track |
Opticomm are laying the fibre to the premise on eligible properties. Completion is anticipated by November 2023. All other aspects of this program/project have been completed. A final report will be submitted to the State Development Department by March 2024, as per funding guidelines once all construction is complete in November 2023.
Mobile:
Broadband:
- ongoing monitoring of nbn on Fixed Wireless upgrades to Logan sites
- ongoing fortnightly meetings with Opticomm are being held to discuss progress & ensure alignment on work and timeframes
Project progress for quarter one 2023/24:
- Milestone 3 – July 2023 Headend Completion – There has been a delay with this milestone due to unforeseen developer activities on the site of the Headend installation. Opticomm are in direct communication with the developer with planned progress and timeframe for the Headend completion to work in with the developer's timeframes. Planned completion date is November 2023. It has been confirmed that this will not delay the entire project deadline as all other work is being completed parallel to this work. With the headend upgrade there will be a network outage of around 2,500 properties. Opticomm will handle the communications with affected residents during affected periods. This upgrade needs to occur during work hours due to the very high risk nature of the work needing to be done in daylight hours. The project in on track for civil completion by end of October 2023. Fibre deployment will occur all in one go for efficiency.
- Milestone 1 - January 2023 Mobilisation has been completed
- Milestone 2 - April 2023 Headend Survey and Design has been completed
- Milestone 4 - Network Detailed Designs - Completed ahead of schedule (originally September 2023, completed in August 2023)
- Milestone 5 - Completion of Fibre Network - due for completion in November 2023
- residents are continuing to register for installation of fibre to the premise – a second works notice was sent from Logan City Council (LCC) in late September 2023. Opticomm will commence door knocking to speak directly with eligible residents in October 2023
- quarterly State Reporting has been finalised and submitted as per updated scope on 13 October 2023
- the next/ last funding release is expected when the project has been finalised, as per contract arrangements, by December 2023/ January 2024
- an Extension of Time (EOT) approval was received by State Development Department on 10 August 2023 (the project was extended to 15 December 2023)
- the final State Development Department payment is due by 15 March 2024
- a site signage exemption approval was received by State Development Department on 8 August 2023.
Mutli Function Edge Data Centre (MFEDC):
- continuing engagement with potential providers
- progressing with formal arrangements & strategic relationship with KalindaIT
- progressing the MFEDC report to apply for further funding from State is on hold.
Low Earth Orbiting (LEO) Trial:
Smart Internet of Internet (IoT) Platform:
|