Conveniently Connected (CC) - Quarter 4 2020/2021
Project | Target | Status | Commentary |
---|---|---|---|
CC1.1.1 - Deliver a report on the medium term needs for Logan's public transport system. Purpose: Identify infrastructure requirements for the City of Logan for the next five to 15 years. |
June 2021 | Completed | A report on the medium-term needs for Logan's public transport system was written to Council to fund the medium-term passenger transport strategy. Council after considering the report indicated that the matter may be considered in a future budget. |
CC1.2.1 - Complete a condition survey of the sealed road network. Purpose: Assess overall condition and prioritise future rehabilitation. |
June 2021 | Not Completed | Field work is completed and 2000km of imagery and data has been provided by the contractor. Due to COVID-19 the processing was delayed but expecting final data of full network condition survey by the first week of August 2021. It is recommended that this project be moved to the 2021/2022 Operational Plan to track its completion. |
CC1.2.2 - Deliver the annual Road Maintenance Program. Purpose: Maintain the quality of the local road network. |
June 2021 | Completed | As at the end of June 2021, 100% of the annual Road Maintenance program of works was delivered. |
CC1.2.3 - Deliver the annual road and drainage capital program. Purpose: Improve active transport across the city. |
June 2021 | Completed | Q4 delivery of the 20/21 Capital Works Program saw a significant increase in expenditure compared to the prior quarter (from $6.5M to $28.7M). At the end of the Fourth Quarter of the 2020/2021 Financial Year, delivery of the Capital Roadworks and Drainage Program has now achieved $63.4 million in overall expenditure. With a number of significant projects recently commencing construction and further key projects well progressed through the procurement stage this momentum is expected to continue into the 21/22 FY. Significant projects, which were underway or completed in the Fourth Quarter include the following:
|
CC1.3.1 - Deliver construction works for the Compton Road cycleway project. Purpose: Link the cycleway to Logan Road and provide connections to the Springwood Bus Station. |
June 2021 | Completed | As at the end of the fourth quarter, planned construction works for this project have commenced for this financial year. Construction of the Compton Road Cycleway is currently ongoing and is scheduled to be completed by August 2021. |
CC2.1.1 - Commission the Cedar Grove Wastewater Treatment Plant (WWTP) in the Cedar Grove Environment Centre. Purpose: Improve services to the southern region of the City of Logan. |
June 2021 | Completed | The Cedar Grove Wastewater Treatment Plant (WWTP) has been commissioned and is treating wastewater from the Greater Flagstone Priority Development Area (PDA). |
CC2.1.2 - Deliver master planning works for the Chambers Flat Wastewater Treatment Plant (WWTP) and associated trunk infrastructure. Purpose: Improve services to the southern region of the City of Logan. |
June 2021 | Completed |
Master planning works of the Chambers Flat Wastewater Treatment Plant site has commenced. The next stage for its completion is dependent on the clarification of a diversion of Chambers Flat Road onto the site. |
CC2.2.1 - Deliver a review of the planning scheme. Purpose: Enable well planned development for residents and businesses. |
June 2021 | Completed | Work on the version 9 Logan Planning Scheme 2015 amendment has been completed and documents are pending delegate sign-off before submission to the State. |
CC2.3.1 - Deliver a review of the Local Government Infrastructure Plan. Purpose: Deliver trunk infrastructure in the City of Logan. |
June 2021 | Completed | As at the end the end of the fourth quarter, the land valuation and feasibility test of the Schedules of Work have been completed and the preparation for community consultation has commenced. |