Conveniently Connected (CC) - Quarter 3 2020/2021
Project | Target | Status | Commentary |
---|---|---|---|
CC1.1.1 - Deliver a report on the medium term needs for Logan's public transport system. Purpose: Identify infrastructure requirements for the City of Logan for the next five to 15 years. |
June 2021 |
Completed
|
A report on the medium-term needs for Logan's public transport system was written to Council to fund the medium-term passenger transport strategy. Council after considering the report indicated that the matter may be considered in a future budget. |
CC1.2.1 - Complete a condition survey of the sealed road network. Purpose: Assess overall condition and prioritise future rehabilitation. |
June 2021 |
On Track |
As at the end of the third quarter, field work for the sealed road condition survey was completed by the contractor. Data processing is scheduled for completion mid-2021. |
CC1.2.2 - Deliver the annual Road Maintenance Program. Purpose: Maintain the quality of the local road network. |
June 2021 |
On Track |
As at the end of the third quarter, delivery of the annual road maintenance program is on track with 75% of the program having been delivered. |
CC1.2.3 - Deliver the annual road and drainage capital program. Purpose: Improve active transport across the city. |
June 2021 |
On Track |
The Capital Roadworks and Drainage Program delivers enhanced transport and drainage infrastructure across the City of Logan. The program delivers infrastructure upgrades to cater for improvements and growth across the city as well as renewal of the existing infrastructure. Significant projects, which were underway or completed in the Third Quarter include the following:
There is currently $116.1 million of projects currently in various stages of pre-construction (including procurement and pre-award assessment) in preparation for construction commencement. This includes:
|
CC1.3.1 - Deliver construction works for the Compton Road cycleway project. Purpose: Link the cycleway to Logan Road and provide connections to the Springwood Bus Station. |
June 2021 |
On Track |
Construction of the Compton Road Cycleway is currently underway. |
CC2.1.1 - Commission the Cedar Grove Wastewater Treatment Plant (WWTP) in the Cedar Grove Environment Centre. Purpose: Improve services to the southern region of the City of Logan. |
June 2021 |
Completed |
The Cedar Grove Wastewater Treatment Plant (WWTP) has been commissioned and is treating wastewater from the Greater Flagstone Priority Development Area (PDA). |
CC2.1.2 - Deliver master planning works for the Chambers Flat Wastewater Treatment Plant (WWTP) and associated trunk infrastructure. Purpose: Improve services to the southern region of the City of Logan. |
June 2021 |
Monitor |
Master planning of the Chambers Flat Wastewater Treatment Plant site has commenced, but will not be completed until the likelihood of a diversion of Chambers Flat Road onto the site has been clarified. |
CC2.2.1 - Deliver a review of the planning scheme. Purpose: Enable well planned development for residents and businesses. |
June 2021 |
On Track |
The Major Planning Scheme Review 2020 resulting in the version 9 amendment to Logan Planning Scheme 2015 will be going to Council for endorsement on Tuesday the 20 April. |
CC2.3.1 - Deliver a review of the Local Government Infrastructure Plan. Purpose: Deliver trunk infrastructure in the City of Logan. |
June 2021 |
On Track |
Work is continuing on LGIP V1.2 however has been delayed due to an additional item being added into the schedule of works. There is an approximate 3 month delay at this time. LGIPV2 has now been extended with a completion date in 2023. |